The three-day community charrette for the Elberta waterfront ended at the Life Saving Station on September 24, and the next public look comes November 12, when the developer's team plans to show a preferred plan. Almost all of the talk this fall has been about the development side, the roughly nine acres working-named Elberta Commons. The larger share of the property, the future village park and the Beach-to-Beach trail, is not decided in that room. It depends on a land transfer, and the transfer depends on a federal grant that is still marked as a recommendation.
Most of the recent coverage treats this as one project. In practice it runs on two schedules, and the one most people in Elberta will feel first is the slower one.
How the 35 Acres Split
When the Grand Traverse Regional Land Conservancy paid $19.5 million for the property on December 13, 2024, the plan already divided the land three ways. Each piece has its own owner, its own approval path and its own next step.
| Parcel | Approx. size | Who holds it now | What has to happen next |
|---|---|---|---|
| Nature sanctuary | 10 acres | GTRLC, permanently | Nothing; it stays as is, with no trails |
| Public park | 16 acres | GTRLC, temporarily | Transfer to the Village of Elberta, funded by grant |
| Elberta Commons | About 9 acres | State Land Bank Authority, with Artemis Companies as developer | Design, then the Village's Planned Unit Development process |
The development parcel starts at the corner of Furnace and Crapo Streets and runs along Betsie Bay. That parcel is the one the charrette was built to shape.
What the Life Saving Station Sessions Were Actually Deciding
The September sessions came at the end of a long summer of input. Webinar #1 aired July 22. Webinar #2 on August 12 presented market research by Sharon Woods of LandUse USA. Focus groups ran August 18 through 20, and two Coffee & Commons mornings were held at the Lighthouse Cafe on July 31 and August 28. All of that fed into the three-day charrette at 1120 Furnace St.
The project's FAQ is direct about what that work does and does not settle. The Village approved Artemis Companies as developer in November 2025, but the development itself has not been approved. Any proposal has to go through the Village's formal Planned Unit Development process. Even the name is temporary. The FAQ calls "Elberta Commons" a working name that may change as the design develops.
The development team has not yet published a summary of the charrette. Its timeline schedules the next few months this way:
| Month (2026) | Scheduled step |
|---|---|
| October | Write a detailed charrette summary; apply the outcomes to the site plan |
| November | Test the feasibility of the concept plan; refine it with the Village, the State Land Bank Authority and GTRLC; Webinar #3 on the charrette findings |
| December | Financial planning, refining the capital stack and incentives for construction |
That is a design-and-finance calendar for nine acres. It does not include a date for the park.
The Park Depends on a Federal Grant, Not a Design Session
GTRLC's Phase II document describes the 16 park acres as land it will "temporarily hold and care for" until they move to the Village. In the meantime it is helping the Village secure public grant money to buy and develop them. In its December 2025 Land and Water Conservation Fund rankings, the Michigan DNR listed the Village of Elberta for $5,347,600 for "Terminus Park Acquisition."
That figure is labeled a recommendation, and the wording matters. The DNR explains that LWCF recommendations need final approval from the National Park Service. MLive reported in December 2025 that a formal grant agreement was still expected before the parkland could transfer. As of GTRLC's June 2026 project page, the park still "will be transferred." The same page showed $26,633,297 raised toward a $27,582,277 goal, leaving $948,980 to go.
Michigan's FY2026 budget also included a one-time $1.75 million DNR appropriation for GTRLC's broader 35-acre project. That money supports the conservation effort as a whole and does not stand in for the park transfer.
Put in order, the public side of the waterfront moves like this:
- The National Park Service approves the LWCF grant and the grant agreement is signed.
- The 16 acres transfer from GTRLC to the Village of Elberta.
- Park work starts: planning, environmental assessments, remediation, removal of old infrastructure and of the chain link fencing along the lakeshore.
- Recreational infrastructure and signage go in later as the project progresses.
None of those steps is on the developer's October-through-December calendar. GTRLC's plan lists the uses the park will eventually open up: access to the lakeshore between the pier heads, fishing in the deepwater channel where migratory fish gather, and bird-watching along a shoreline where Bald Eagles and monarch butterflies are often seen. For anyone who follows the fall runs we covered in our guide to the Betsie and Platte salmon season, that channel access is the item to watch.
The Trail Is Where the Two Schedules Meet
The Beach-to-Beach segment of the Betsie Valley Trail would connect the Frankfort and Elberta Lake Michigan beaches and tie into 22 miles of existing trail. The Village has easements for every other parcel the route needs. GTRLC kept an easement through the property so the trail can be built no matter who owns the land later.
The route is protected, but nothing will be built until the land transfers. GTRLC's document says the Village plans to apply for construction grants after the transfer. On April 16, 2026, the Elberta Village Council approved a letter supporting the proposed DNR extension of the trail to Elberta Beach.
The trail is also the one public piece the charrette did shape. The Friends of the Betsie Valley Trail summer 2026 newsletter said input from the September visioning would guide the trail's design, its route through the Village and its end point at Elberta Beach. So the design is being drawn on the faster schedule, while construction waits on the slower one.
The same newsletter shows how grant-paced trail building tends to go. The Friends had planned to pave about a mile from the new Thompsonville trailhead park to the Betsie River trestle this year. That work slipped to next spring because of the drawn-out state budget process, even though the Trust Fund grant had been recommended the previous November. For the next 6.3 miles, which depend on more grant approvals, the earliest expected completion is 2028. A recommendation is a strong signal, but the trail organization's own timeline shows it is not a start date.
Ten Acres That Will Look the Same in Ten Years
The steep, forested dune at the north end of the property is the one piece with no next step. It sits in a state-designated Critical Dune Area at the northern reach of a parabolic dune system that rises 280 feet above Lake Michigan. GTRLC is clear about its future:
Because this area is less suited for the types of access typically found in parks, it will not feature any trails or recreational infrastructure.
The conservancy cites boreal conifers that give migrating warblers, Scarlet Tanagers and Wood Thrushes places to nest and feed. It is the backdrop for whatever gets built along the bay, and it is not part of any plan to change.
What Is Open to You This Month
None of this pending work changes the parts of the waterfront Elberta already uses. The Village's beach page lists public access to Elberta Beach from the Bye Road parking area and through two easements off Lakeside Boulevard. The Village recreation plan's inventory for the existing Waterfront Park includes the Life Saving Station, the historic ironworks ruins, a fishing pavilion, a picnic pavilion, a playground, fitness equipment and paved paths.
For the land GTRLC is holding, the most recent public statement is from October 2025. At that time, MLive reported that GTRLC intended to keep existing access to Elberta Beach and the overlook unchanged, while access to the expanded parkland was still being decided. We found no 2026 update to that statement.
The bayfront also gets a crowd on Saturday, October 10, when the Frankfort Fall Festival runs from 11 a.m. to 6 p.m. The Port City Run 5K starts at 9 a.m. and follows Betsie Bay into Elberta, and the craft fair runs from 10 a.m. to 4 p.m. at Open Space Park. That route covers the same shoreline the Beach-to-Beach segment would eventually connect. For a stop afterward, The Patch at 401 Main St. in Frankfort opened this summer with bowls, salads and wraps. It is run by Beth and Tony Roethler, who also own the Cabbage Shed in Elberta.
The next public look at the development parcel is Webinar #3, set for November 12; RSVP details are on the Elberta Commons events page. Fundraising progress for the park and sanctuary is posted on the GTRLC project page. More about the shoreline communities from Frankfort south is on our Lake Michigan page.
If you own near Betsie Bay and want to understand how the park transfer, the trail route or the PUD review could affect your street, The Jon Zickert Group follows each step and is happy to walk through it with you. Schedule a consultation and we'll go over what's settled and what is still pending.